Use the EDI 852 Complete Refresh option in the 852 Product Activity Report Setup to purge all the records from the file the 852 Product Activity Report uses, so the next scheduled report using the Changes Only option generates for all selected items.
To perform an EDI 852 complete item refresh:
From the System > System Programming > EDI > EDI Generate Reports > EDI 852 Product Activity Report Maintenance menu, select 852 Product Activity Report to display the EDI 852 Product Activity Setup screen.
Note: If prompted, log on to the character-based system.
In the 852 Accumulation Type field, select Complete Refresh and enter the date from which the purge should begin in the Start Date field.
Schedule the 852 to run as follows:
Use the Opts hot key and select scheduling to display the Phantom Scheduler screen, where you can schedule this report to run at regular intervals. Schedule the 852 to run after hours, when item activity is quiet.
After you press Esc to exit the Phantom Scheduler screen and return to the EDI 852 Product Activity Setup screen, use the Hold hot key to schedule the job.
See Also: