The following control maintenance records belong to the WIP (Work Order Processing) category.
Use this record to enable automatic reconciliation of the setup and
material costs on a work order. More:
Options |
Important: If you want the system to record the process cost for each step when backordering work orders, you must select this option and set the Method For Calculation process Qty For Work Orders control maintenance record to In to Stock.
|
Outcome of setting this control record |
Determines if the system auto reconciles the setup and material costs on work orders. See the detail above for further explanation. |
Default Value(s) |
By Step |
Action if set to Null |
Off |
Additional Information |
If you plan to use auto reconcile once you have created the template to get the cost of the finished product going back into stock, we recommend that you select by In/Out Grouping and have the system do it for you when you escape out of the Material Details window. |
Indicate the default step to use on the work order that is created when
you enter product cuts on an order, and for the final process for cut
products. More:
Settings |
|
Outcome of setting this control record |
Determines the default first step and the final process step |
Default Value(s) |
Blank |
Dependencies |
The system validates
your entries based on the |
Action if set to Null |
Steps are not assigned by default. |
Additional Information |
For more information, see Statuses for Cut Product Work Orders. |
Indicate whether the system displays all process comments, either predefined
standard comments or comments entered manually, in the body of the work
order and when printing steps. More:
Options |
|
Outcome of setting this control record |
Determines if the work order comments are included in the body of the work order. |
Default Value(s) |
Yes |
Action if set to Null |
Process comments to do not display. |
Additional Information |
For more information, see Adding Comments to Work Order Processes. |
Select the method to use for calculating process quantity for work orders.
More:
Options |
Important: If you want the system to record the process cost for each step when backordering work orders, you must select this option and set the Auto Reconcile Work Orders control maintenance record to by Step.
|
Outcome of setting this control record |
Determines when a work order product is considered part of the process quantity. |
Default Value(s) |
In to Stock |
Action if set to Null |
Same as if set to Out of Stock. |
Additional Information |
None |
For each branch, select whether the system re-sorts items on a work
order by location when the order step is processed and, if so, how it
re-sorts them. More:
Options |
|
Outcome of setting this control record |
Re-sorting can facilitate putting away the order. |
Default Value(s) |
Blank |
Action if set to Null |
Same as if set to No. |
Additional Information |
If you set a branch to Primary Loc or Line Item Loc, unattached comments sort to the top of the list, since they do not have an assigned location. |
Select whether to update the cost on a sales order containing items
that are tagged to a work order when a cost changes on the work order.
More:
0 (No update) - The cost on a sales order containing items that are tagged to a work order is not updated when a cost changes on the work order.
1 (Update open Gens) - The system copies the price change back to all quantities on the open generation of a sales order tagged to a work order to make sure that the cost on the order is the same as the tagged work order price. This is only effective when you change the cost on the work order itself, and only if the entire quantity for the line item on the generation is tagged to the work order.
2 (Update open and closed Gens) - The system copies the price change back to all quantities on both open and closed generations of a sales order tagged to a work order. The closed generation must still be in an open accounting period.
Select whether to update an item's cost in the materials list on a work
order based on the cost of the tag when procuring material in order to
fulfill a work order. More:
0 (No update) - The cost of an item on a work order that is tagged to a purchase order is not updated by the cost on the purchase order.
1 (Update open Gens) - The system only updates the item's cost on the purchase order if the item is on a step that is currently in an open status.
2 (Update open and closed Gens) - The system updates the cost of all the items on the purchase order for any step in an open or closed status.
The system updates the cost on the purchase order on initial creation of the tag and then any time the cost on the tag changes.
Note: This control maintenance record will not update any Small Project Job line items on any order so that the Small Project Job contract is respected. Updated in Release 9.0.5.
Select whether to update an item's cost in the materials list on a work
order based on the cost of the tag when transferring material from a branch
in order to fulfill a work order. More:
0 (No update) - The cost of an item on a work order that is tagged to a transfer order is not updated by the cost on the transfer order.
1 (Update open Gens) - The system only updates the item's cost on the work order if the item is on a step that is currently in an open status.
2 (Update open and closed Gens) - The system updates the cost of all the items on the work order for any step in an open or closed status.
The system updates the cost on the work order on initial creation of the tag and then any time the cost on the tag changes.
Enter the processes, such as welding, plating, bending and cutting,
that you sent to service vendors. More:
Options |
Any free form text up to 15 characters each. |
Outcome of setting this control record |
The work order
processes defined here are available for assigning in Work
Order Entry and the |
Default Value(s) |
Blank |
Action if set to Null |
No steps are available in Work Order Entry. |
Additional Information |
None |
Indicate how the system determines the shipping and pricing branch for
work orders created from the Suggested Work Order window, the OE Schedule
window, and a copied work order. More:
Settings |
|
Outcome of setting this control record |
The settings you enter here determine how the system sets the shipping and pricing branch for work orders. |
Default Value(s) |
No for all fields. |
Action if set to Null |
Same as if set to No. |
Additional Information |
None |
Select the default G/L account to credit, instead of the Work Order
Holding Account, in the case when a work order does not have incoming
material on any steps and all of the steps have been set to Complete.
More:
Options |
Any general ledger account defined in your system. |
Outcome of setting this control record |
Use this record when you send material out for testing and do not expect or want to put the material back into inventory when the testing is finished. It might be that the material is destroyed and cannot be put back into inventory. |
Default Value(s) |
Blank |
Action if set to Null |
Uses the Work Order Holding account. |
Additional Information |
For more information, see Creating G/L Accounts for Work Orders. |
Enter a pay-to vendor for the system to use to calculate the price for all outgoing material (material coming out of stock) on a work order.
Indicate whether the system prompts users to enter a multiplier quantity
when they copy
a work order template to a work order. More:
Options |
|
Outcome of setting this control record |
Determines if the system creates the work order with the quantities specified in the work order template, or if it prompts for the quantity by which it multiplies the quantities in the template. |
Default Value(s) |
No |
Action if set to Null |
Same as if set to No. |
Additional Information |
None |