The Suggest P/O program has two different ways of determining when a parent branch needs to make a purchase to meet a child branch's needs. The method used depends on the parent branch's lead time and the child branch's Transfer Cycle Days.
The other calculation that is prevalent throughout the Purchasing process is the projected inventory level or PIL. The PIL is the quantity of a product used for predicting purchasing needs. The amount you physically have on hand, minus the amount committed to orders, plus the amount coming in on transfers and purchase orders. Each product has its own projected inventory level.
PIL = ((available on hand/committed) + on transfer + on purchase order + in process/work)
Note: If the
This section describes two examples each showing one of the methods:
If the parent branch's lead time is less than the child branch's transfer cycle days, then to meet the child branch's needs the parent branch must purchase enough to meet the child branch's transfer cycle days.
If the parent branch's lead time is greater than the child branch's transfer cycle days, then to meet the child branch's needs the parent branch must purchase enough to meet the parent branch's lead time requirements.
Regardless of the method used, the Suggest P/O program uses two constants: the child branch's demand and the child branch's hit-related safety coefficient (HRSC).
The standard surplus point is defined as the point at which the stock level for inventory is greater than the economic order quantity plus the line point rounded to package quantity.
The surplus point calculation for the parent in a grandparent/parent/child warehouse scheme is as follows:
Parent Surplus Point = ((Lead Time plus Cycle Days plus Safety Days (LCS) of grandparent )multiplied by the Combined Demand per Day (
Abbreviated: (LCS x
Note: For new product minimum and maximum settings, see Setting Minimum and Maximum Stocking Levels for New Products.
In the following example, assume that the parent branch's projected inventory level equals the order point.
In other words, the parent branch has nothing to spare, but also has no needs. The only thing the Suggest P/O program needs to determine in the example is how much to buy for the child branch.
Premise: When the parent branch's lead time is less than the child branch's transfer cycle days, to meet the child branch's needs the parent branch has to buy enough to meet the child branch's transfer cycle days.
The transfer cycle days of the child branch is 90. This number exceeds the parent branch, which is 30. The child branch's short quantity trigger is based on its transfer point. The parent's lead time is not used because the child branch's need is more.
Parent Branch's PIL |
24 |
Parent Branch's Order Point |
24 |
Child Branch's PIL |
11 |
Child Branch's Transfer Point |
92 |
The parent branch must buy 81 to meet the transfer point of the child branch. |
|
Child Branch's Transfer Point minus the Child Branch's PIL: 92 - 11 = 81 |
In the following example, assume that the parent branch's projected inventory level equals the order point.
In other words, the parent branch has nothing to spare, but also has no needs. The only thing the Suggest P/O program needs to determine in the example is how much to buy for the child branch.
Premise: If the parent branch's lead time is greater than the child branch's transfer cycle days, then to meet the child branch's needs the parent branch must purchase enough to meet the parent branch's lead time requirements.
The parent branch's lead time is 30. This lead time is greater than the child branches transfer cycle days, which is 14. The parent branch's lead time is used to establish the child branch's order point, which is then used to calculate the amount to buy.
Parent branch's lead time is multiplied by the child branch's demand per day. The result is added to the child branch's safety stock multiplied by the child branch's demand per day. This is equal to the child branch's order point, as shown below:
(30 x 0.751) + (19 x 0.751) = 37
Child branch's order point minus the child branch's PIL equals the amount the parent branch needs to purchase.
Parent Branch's PIL |
24 |
Parent Branch's Order Point |
24 |
Child Branch's Lead Time |
30 |
Child Branch's Demand Per Day |
0.751 |
Child Branch's HRSC |
0.62 |
Child Branch's Order Point minus the Child Branch's PIL: 37 - 11 = 26 |
See Also:
Setting Minimum and Maximum Stocking Levels for New Products
How the System Calculates Line Point Safety Days